Wardrop Delivers Positive Preliminary Assessment for Songjiagou Gold Project

Vancouver,British Columbia, January 20, 2011. Majestic Gold Corp. (TSX.V:MJS, Frankfurt:P5E) is pleased to announce that Wardrop, A Tetra Tech Company, (Wardrop) has completed and delivered a positive Preliminary Assessment (PA or Preliminary Assessment) for the Songjiagou Gold Project located in Shandong Province, People's Republic of China.

Highlights are as follows:
  • Net Present Value of US $525 million using a 10% discount rate
  • Internal Rate of Return of 78.6%
  • Payback in 1.4 years
  • Total gold production of 2.324 million ounces (average 105,645 oz/yr) for life-of-mine
  • Life--of--Mine strip ratio 1.87:1 (waste to ore)
  • Mine-Life of 22 years.
"The Preliminary Assessment provided by Wardrop has exceeded our expectations and will form the basis for our continued development of the Songjiagou project" stated Rod Husband, President and CEO of Majestic Gold Corp.

A summary of the main sections of the Preliminary Assessment are as follows:

Resource

In 2006, Wardrop prepared a National Instrument 43-101 (NI 43-101) compliant, resource estimate of the Songjiagou deposit. On the basis of additional data collected during 2006, Wardrop prepared an updated estimate in late 2007.

In April 2010 Wardrop completed an update of the 2007 resource estimate to take into account assay results from surface core drilling and trenching that were carried out during 2007, as well as depletion from surface mining since the time of the last estimate. Depletion attributable to underground mining during the same interval was negligible.

The April 2010 updated resource estimate was made using an un-rotated block model, which is to say the blocks in the model were oriented orthogonally east-west and north south. In October 2010, Majestic requested that the estimate be redone using a block model rotated parallel to the trend of the deposit as well as a lower cutoff (0.3 g/t versus 0.4 g/t gold).

The lower threshold grade (0.3 versus 0.4 g/t) is attributable to a lower cost for contract mining and milling that Majestic negotiated during the period between the two estimates.

The rotated orientation is consistent with previous estimates and also aligns the block model with cross-sections that are cut perpendicular to the strike of the deposit. The change in block model orientation as well as the decrease in cutoff grade resulted in an overall enhancement of both estimated tonnes and grade. This report incorporates those changes. There has been no change in the underlying data between the April 2010 estimate and the current estimate.

The resource used in preparation of the Preliminary Assessment is tabulated as follows:

*Resource Categroy Cut-off (g/t) Tonnes Au Uncap g/t **Au Cap g/t Ounces Au Uncap Ounces Au Cap
Indicated 0.30 33,739,586 1.384 1.147 1,501,298 1,244,211
Inferred 0.30 38,812,054 1.500 1.467 1,871,755 1,830,576
 
*The preliminary assessment includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary assessment will be realized. All figures have been rounded to reflect the relative accuracy of the estimates **gold grades were capped at 40.0 g/t

Open pit optimization was carried out using WhittleTM 4.3 which uses a series of Lerchs Grossman (LG) pit shells at different prices of gold to optimize the size of the pit while maximizing net present value (NVP) of the deposit. The resulting LG shells generated the highest discounted cash flow from the ore body at varying prices of gold. The LG shell used for optimization does not apply practical mining considerations and constraints.

The strategic planning using the generated LG pit resulted in the following potential mineable resources, which forms the basis of the preliminary Assessment:

*Potentially Mineable Resources Classification Tonnes Grade, Au(g/t)
Indicated 29,875,527 1.207
Inferred 22,806,473 1.936
  *Potentially minable resources include the inferred mineral resources and are not mineral reserves.

Preliminary production schedule

The life-of-mine strip ratio is 1.87 to 1 (waste to ore). Total ounces contained in the resource are 3,074,787; of these, 2,324,000 ounces are potentially recoverable as bullion during the mine operations at an average annual production of approximately 106,000 ounces per year.

The attached preliminary production summary table summarizes the information from the preliminary economic assessment production schedule.
Preliminary Production Summary

Unit Years 1-8 LOM  
Process Feed
Gold

g/t

2.12

1.52
Material Mined
Mill Feed
Waste
Ore Mined

kt
kt
kt

18,494
47,746
18,494

52,682
100,377
52,682
Strip Ratio   2.33 1.87
Total Production
Gold

koz

1,152

2,324
Average Production
Gold

koz

144

106

The following table details the planned Production Schedule for the Life-of-Mine:

Preliminary Production Schedule

Tonnes mined including stockpile are in the potentially minable resources category. The preliminary assessment includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary assessment will be realized.

Capital Costs

Total capital costs are estimated at $129.2 million including initial capital, initial working capital and sustaining capital. The majority of sustaining capital is required in years 4 and 5 and consists mainly of capital required to expand tailings storage facilities. A more detailed breakdown of the capital costs is provided in the following table.
Capital Costs  

  Pre-production (pre-strip)
  Initial Capital
  Initial Working Capital
  Sustaining Capital
000's US$
0
64,377
7,120
64,787,
Total Capital Costs 122,163


Operation costs

Life-of-mine operating costs are estimated at $11.67 (U.S.) per tonne milled, including mining, process and transportation costs based on the current contract terms. The details of these costs are in the attached operating costs table.
Operating Costs  
US$/tonne milled
  Mining, Process and Transport
  G&A and Quality Control
10.72
0.95
Total Operating Costs 11.67


Operating cash flows

Operating cash flows based on pit optimization limits employed by Wardrop indicate that, in years one to eight, the mine will approximately produce a total of 1,152,000 ounces of gold (144,000 ounces annually) and generate $841-million (U.S.) ($105-million (U.S.) annually) in operating cash flow compared with life-of-mine production of 2.32 million ounces of gold in concentrate (106,000 ounces annually) and operating cash flow of $1,516-million (U.S.) ($68.9-million (U.S.) annually).

The projected cash flows are tabulated below.
Operating Cash Flow  
Years 1-8
  Total
  Average
LOM
  Total
  Average

841,344
105,167

1,515,927
68,906


Economic returns

Wardrop evaluated the economic viability of the Songjiagou project using pretax discounted cash flow analysis based on the engineering work and cost estimates discussed in the preliminary assessment. Over the life of the mine, Songjiagou is estimated to produce on average of 106,000 ounces gold in concentrate per year. Total gold produced for LOM will be 2,324,000 ounces; with a gold price of $973 per ounce and total operating cash flow of $1,516,000, the total cash cost is $745-million (U.S.) or $321 (U.S.) per ounce of gold. The pretax net present value is $525-million (U.S.), and the internal rate of return is 78.6 per cent.

The attached economic returns table illustrates the project NPVs using various discount rates besides the 10-per-cent base case.

Economic Returns  
Project NPV
14.0% discount rate
12.0% discount rate
10.0% discount rate
8.0% discount rate

Project IRR

Payback
Mine Life
Unit
million US$
million US$
million US$
million US$



Years
Years
Pre-Tax
381
446
525
624

78.6%

1.4
22


Sensitivity analysis

Sensitivity analysis was conducted for gold price, exchange rate, gold feed grade, operating costs and initial capital costs over a plus/minus 30-per-cent range. The results are shown in the attached sensitivity analysis table.

Sensitiviy Analysis (in US$ millions)  
  NPV @ 10% discount rate
Variable
Gold Price
Exchange Rate
Gold Feed Grade
Operating Cost
Initial Capital Cost
-30%
276
553
277
586
542
-20%
359
544
360
566
536
-10%
442
534
442
545
531
0%
525
525
525
525
525
10%
608
516
608
505
520
20%
691
507
691
485
514
30%
774
497
774
464
508


As the table shows, the main factors impacting the NPV are gold price and gold feed grade, while exchange rate, operating costs and initial capital costs have a much smaller effect on NPVs.



Based on the estimates in the preliminary economic assessment, Majestic plans to move ahead with continued development of the project, including more detailed engineering studies and applications for mining permits.

The preliminary economic assessment was prepared by Wardrop consultants, all of whom are independent of Majestic and are qualified persons as defined by Section 1.4 of National Instrument 43-101. The QPs have reviewed and approved the information in this news release. The consultants with their responsibilities are as follows:
  • Wardrop, under the direction of Greg Mosher, PGeo, for all matters relating to geology and mineral resource estimate;
  • Wardrop, under the direction of Nory Narciso, PEng, for all matters relating to mine planning, mine design and report co-ordination;
  • Wardrop, under the direction of John Huang, PEng, for all matters relating to mineral processing, metallurgical testing, infrastructure, tailings management facility, environmental impact considerations, licence and permit, operating and capital cost estimates, and smelting terms;
  • Wardrop, under the direction of Miloje Vicentijevic, PEng, MEng, for all matters relating to economic analysis.


Click here to view Complete 43-101 Report